Engineering Day
Final Year Project
Development of SCADA System Integrated with Motor Control Center
Tuesday, April 24, 2012
Week 15
Final year project presentation
Engineering Day
Engineering Day
Friday, April 20, 2012
Week 14
Final test for the function of the project
Everything is already put in the box
Ready for testing
Display on Visual Basic.
This is at main trip and back up off condition
When the back up turn on back using SMS.
The indicator of back up will green.
Friday, April 13, 2012
Friday, April 6, 2012
Friday, March 30, 2012
Week 11
Study on visual basic software to enable it to communicate with PC.
Microsoft visual basic is used to monitor system via PC.
Signal from the system will be sent to the GSM.
Condition of system will be show at PC.
It can make easy to monitor the system.
Microsoft visual basic is used to monitor system via PC.
Signal from the system will be sent to the GSM.
Condition of system will be show at PC.
It can make easy to monitor the system.
Friday, March 23, 2012
Week 10
Finding a electrical part.
Relay
Relay omron 240VDC will use.
Contactor
Relay
Relay omron 240VDC will use.
Contactor
- LS Industrial Metasol Contactor - 9A, 3 Pole,
- Screw Clamp Terminal,
- 600V, 230VAC / 60Hz Coil,
- 1 N.O. / 1 N.C. Aux.,
- Compatible Overload Relay MT-32
- 3 Pole(NO) main contact
- Finger proof design
- DIN rail or screw mountable
- AC or DC control in different physical size
- Front/side mountable accessories available
- Direct mountable overload relay available Rating
Friday, March 16, 2012
Week 9
Preparing for electrical part.
Finding a diagram for contactor.
Finding a part for motor contactor.
Chose suitable relay for circuit.
Finding a diagram for contactor.
Finding a part for motor contactor.
Chose suitable relay for circuit.
Friday, March 9, 2012
Week 8
Construct RS232 for connecting with PC.
This circuit using max232 in operating.
This circuit using max232 in operating.
MAX232 based level shifter IC
Simple and straight forward design
Easy connection to your HOST interface
Supply provided by the host interface.
Friday, March 2, 2012
Week 7
Soldering circuit with componen as a schematic diagram.
Using push button for temporary while for testing.
LCD will display the condition of system.
Friday, February 24, 2012
Week 6
Briefing at Gemilang Hall on 16 Feb 2012.
Brief discussion about the format of reports should be sent at the end of this semester.
Trying to develop a circuit.
Etching printed circuit board.
Brief discussion about the format of reports should be sent at the end of this semester.
Trying to develop a circuit.
Etching printed circuit board.
Friday, February 17, 2012
Week 5
PCB layout
- The PCB layout is a mirrored positive one - black on white.
- Mirrored as viewed from the silkscreen top (component) side.
- The PCB layout is printed 1:1 on paper by means of a laser printer or copier machine.
- The laser printer or copier toner will not run out when it gets wet or oily.
- The ink of an inkjet paper print does run out and inkjet printers are therefore useless with the described method.
Circuit Diagram
- Very popular microcontroller.
- A lot of references and a very good supports by the manufacturer
- So many choices of microcontroller design with different function and application
Friday, February 10, 2012
Week 4
Summary of the flow circuit
Main switch will control circuit in normal condition.
The system will display the condition of motor control system in PC
When a main switch failure, PC will display a main switch trip and at the same time SMS will send to mobile phone.
To turn it back, SMS will replay with a command BACKUP ON or also can turn it on with manually.
Backup just for temporary.
If backup also trip, this system will totally off and will display in PC and sending SMS.
In this condition, system should will turn on manually.
Friday, February 3, 2012
Friday, January 27, 2012
Week 2
Second briefing for the final year project at Gemilang Hall
This briefing is a lot of explaining to students the importance of FYP.
This briefing is a lot of explaining to students the importance of FYP.
Friday, January 20, 2012
Week 1
Briefing about final year project at Gemilang Hall.
Identify equipment that will be used in this project.
Find the necessary equipment as planned.